wpe2.jpg (17885 bytes)

Engineering Work Plan & Forecast

In anticipation of rapid account growth and facilities that are in some cases nearing the extent of their useful life, Tideland EMC’s board of directors gave the green light to accelerate expenditures on electric system improvements starting in 1998. Since that time we have invested more than $20 million in system improvements. Construction expenses cover four areas of operation: transmission, substation, distribution and consumer services. Highlights of the projects in each operational district including systemwide consumer services follow.

Engelhard District
Chronic problems with North Carolina Power's Fairfield delivery point (where power actually changes hands from NCPower to TEMC) have resulted in a power supply outage rate of 17.4 hours per consumer in the Engelhard District. Mutual aid plans that allow TEMC personnel to identify and repair problems along the NCPower system have been marginally beneficial. Therefore, Tideland will abandon the Fairfield delivery point in the next four years and the Engelhard District will receive its power from a 115kV circuit that originates at TEMC's Pantego substation. The circuit will run to a new Lake Mattamuskeet substation (substation cost: $1.372 million) where it will be stepped down to 35kV. From there a new transmission line will go from the Lake Mattamuskeet substation to the existing Fairfield substation. A total of 24.7 miles of new transmission line will be built.
Project cost: $9 million     Completed: December 10, 2001

NC Department of Transportation will install power line attachment inserts on the new Croatan Sound Bridge currently under construction. The inserts will make it possible for TEMC to run power lines from Manteo to serve the members of mainland Dare County.
Construct a new substation at Manns Harbor and tie in to a new NC Power delivery point in Manteo.
It is six miles from the new delivery point in Manteo to the site of the new MannsHarbor substation. That means more than 80 miles of power line exposure will be eliminated in the delivery of electric service once Tideland energizes the new substation.
Cost: $1.5 million       Completed: January 29, 2003

Grantsboro District
A second circuit will be run from the Silver Hill substation along Highway 33 in Pamlico County to the Fairfield Harbour area in Craven County to alleviate load problems. We will also replace a single-phase underwater cable to the area with a three-phase cable to accommodate continuing growth in the area.
Project cost: $400,000         Completed in 2000

Rebuild approximately twenty miles of power line between Cypress Landing and the Edward substation. Building four miles of new power line in the area as well. Extensive tree trimming in the area prior to construction.
Project cost: $1 million    Start Date: November 2002    Completion: Summer 2003

Pantego District
Upgrade the 35kV line that runs 10.1 miles from the Five Points Substation across Highway 32 to the Washington Substation in the River Road area to 115kV.
Project cost: $1.75 million     Completed in 2001

Convert the Pantego 12.5kV circuit to 25kV and relocate the Pantego transformer to the Sidney substation. Upon completion we will have in place an alternate feeder to the Sidney substation which is essential since the existing feeder crosses both the Pantego and Pungo Creeks with underwater cable.
Project cost: $768,800         Completed in 2001

Ocracoke District
The sole connection between Hatteras and Ocracoke Islands is a 3.5 mile, 35kV underwater cable installed approximately 12 years ago. To date the line has been spliced eight times and the continual shifting of sand in the channel bottom has exposed the cable in many locations. A second cable will be installed and buried approximately six feet below the channel bottom.
Project cost: $1.255 million     Completed in 1999

[top of page]

[Home] [Currently] [About TEMC] [Tech Talk] [Products & Services] [Bright Ideas] [Newsletter] [Library] [Site Map][Safety] [Reliability Issues] [Work Plan] [Outage Information] [Glossary]
[Contact Tideland EMC]